The video illustrates handling progress in Multi·Project·Planner.
Progress in Multi·Project·Planner is defined as:
- The anticipated duration of the activity. (The black bar)
- The current progress, i.e. the amount of the work finished. (The figure within the yellow box)
- The date at which these figures were set. (The placement of the yellow box)