Gantt charts
This picture illustrates Multi Project Planner's implementation of Gantt charts.
A single project is highlighted and the interrelationships between its activities shown.
|
The tool tip describes the relative constraint between 'Bricklaying' and 'Roofing', saying that
|
When dragging the project along the plan, the relative constraints are respected, ie when 'Bricklaying' meets an obstacle it will rest until the span between it and 'Roofing' reaches 10 working days, at which point it will start moving again. The video Moving a project illustrates the point. For a more complex example see Home Construction Co. |